Steel works
Fabrication of different types of platforms and foundations for KWINT Offshore
4-8
January 2019 - project continues
Baskets
Fabrication of offshore baskets for installation and storage of cables for Damen Shiprepair Harbour and Voyage
30
June 2018 - project continues
MPI Adventure
Different types of demobilisation and mobilization works
16
September till October 2021
Hidden Gem
Assembly and installation of LARS system
10-20
August-September 2021
Sixtine
Steel renewal
8
Aprill 2021
Cleaning barges/vessels after project
Demolition works (gauging, grinding, cutting)
16
2021
XIANG-HE-KOW
Demolition of platform, weight 5200 ton
25
October 2018
Aeolus
Prefabrication and installation of Deck sections and Spoonsoons
100 - 130
October 2017 till May 2018
Barges GB-1, GB-2 & GB-3
Sea fastening for transportation wind energy sections
Fitting and welding new constructions
10-15
March 2017
emssun
Shell repair WBT 4SB 800*600*12
Removal of 125 pcs Anode protections
Renew Stainless steel propeller caviation ring in bow thruster tunnel Ø1272x300x12mm
12
April 2016
Stena Hollandica
Several steelworks incl. renewal funnel, transport holes
Fitting of rudderbulb on existing rudder
Rudder Bulb and Fairing Cone ü Connections
30 - 50
February 2017
Concordia
Installing of 18 new container sockets
2
April 2016
Tom Sawyer
Different steelworks.
35
December 2016
Mona Swan
Forecastle Deck Bulwark Repair (SB Side)
Main deck renewal
10
April 2016
Innovation
Steelworks assembly of 4 pcs spudcan shoes
Extending the access trunk on top of the spudcans
Side shell repair
Fender supports installation
Anodes installation
50
November 2016
Selandia Seaways
Taging supports installed/removed Main Hinge sternramp PS
4x support HINGE STERNRAMP
Cracks repair and insert plates
12
April 2016
Bore Bank
Installing of 530 container fittings.
15
February 2017
Stena Britannica
Several steelworks incl. renewal funnel, transport holes
Fitting of rudderbulb on existing rudder
Rudder Bulb and Fairing Cone ü Connections
30-50
Nov 2016
Panton
Welding of a 10 tons Pad ayes
2
March 2016
Ridgebury Catherine Z
Top plate of bulbous bow to be partly cropped and renewed
6
September 2016
Stena scotia
Replace of insertplate in Hull execution
4
March 2016
stornes
Renewal of hull plating in area of WBTK 125
Install stainless steel striking plates in Holds
Install of ADCP Steelworks
Welding job in FWR Bow thruster
20
March 2016
Sea bear
Replacement of PS shaft generator
Preparing and modificate foundation for replacement of generator
8
March 2016
Citius
Bottom and Rudder damage
Main activities: Remove the rudder for repair in the workshop and renew 30 t. bottom
1. Preparation works for remove the rudder: transport holes to remove pins and main shaft, acc. op. to remove rudder
2. Bottom damage: forepeak, WBT 1, 2, 3 PS/SB (internals, BHD, bottom plates)
30-40
February 2017
PETROJARL 1
Assistance for removing rudders, steering gears and tail shafts.
All steel works
20-130
April 2015 till August 2017
British falcon
small steel works
4
Feb 2016
G501 and G502
Steel renewal 55 tons.
30
May 2016
Esnaad 223
Steel repair shell plate tank 5 SB 2400*500*9
4
Dec 2015
Thorco gougar
Welding of Ballast tanks
10
Dec 2015
Fugro scout
A-Deck modification SB and PS at Fr. 0 to -5.
a lot of small steel works
installation of new equipment for new project
20
Dec 2015
Stella maris
Renewal of hull plating SB Tank Tank 1&2 SB
12
Nov 2015
Bow Triumph
Steel repair deck plate WBT 1&2 SB
Handrails to be renewal
8
Oct 2015
Dianthus
Replace and reweld of the Thruster Gratings
2
Sept 2015
Eems Transporter
Hull damage repairs
6
Sept 2015
NouNou
Assistance for steel damage repair
Steelrepair of Hull welding in ballast tank no. 5 & 6
8
Sept 2015
Elite
Refit of overhauled Bow thruster incl.
4
Aug 2015
Yasmine
Hull damage to be repair
10
Aug 2015
Prima Dora
Closing lock between section 19/21 to be renewal SB
Hatch stress points repair
Pipe penetration to be renewal
Steel renewal WBT 3 PS
Welding goose neck on the top of the bridge
16
July 2015
Rita
Reffiting and welding of the rudders inspections plates
4
July 2015
Union Princess
renewal hull damage
July 2015
Stan patrol
Steek work to vessel bowand externals
6
July 2015
Seven discovery
Bottom plate to be repaired
8
July 2015
Volvox Olympia
Hull damage to be repaired
12
June 2015
Geopotes 15
Mechanical and steel works
40
Jun - Sept 2015
FREYA
Renewal access plates on rudder blades
4
April 2015
ESPACE
Bottom plugs to be removed
2
April 2015
GLOBAL 1200
Modification and conversion of vessel
15-90 workers
March - June 2015
Osv relume
Platforms around crane 2
Platformsaround crane to be placed around crane
10
April 2015
Pacific Champion
Modification and preparation vessel for new project ( steel works)
20
April -May 2015